A press rebuild in seventy-two hours

Home

Blog

An engineer in an orange hard hat and hi-vis vest pointing along a huge machined shaft in a workshop

At four on a Friday afternoon a supplier of pressed steel panels rang our breakdown line: the main cylinder on their 1,200-tonne press had cracked, and the line fed a car plant that expected parts on Tuesday morning.

Friday: find out what is actually broken

Two engineers were on site by seven. By midnight the cylinder was out, the crack was measured and photographed, and our fabrication shop had the drawings. A new cylinder would take eleven weeks; a repair would take two days if the shop started at dawn.

We did not need a meeting. We needed someone to tell us what was going to happen and when, and they did that every four hours.

Fannie Rowe, plant manager

Saturday and Sunday: machine, weld, test

The shop machined out the damaged section, welded in a new sleeve and pressure-tested it to one and a half times working pressure. On site, the crew replaced every seal and hose they had disturbed rather than reusing them.

Monday: run it in

The press ran its first trial stroke at two on Monday afternoon and full production at six. A new cylinder is on order, and the repaired one will come out at the planned summer shutdown.


One response to “A press rebuild in seventy-two hours”

  1. Daniel Osei Avatar
    Daniel Osei

    Useful write-up. We keep a spare seal kit for every press now after a similar weekend last year.

Leave a Reply

Your email address will not be published. Required fields are marked *